SCDOT Design-Build Projects in Construction


Project Name RFQ Announcement
of Short-listed Teams
RFP
Industry Review
Final RFP Public Announcement Notice
of Award
Notice
to Proceed
Bid
Summary
Anticipated Substantial Completion
Closed and Load Restricted Bridge Package 2021-1 03/31/2021 06/15/2021 06/21/2021 08/10/2021 02/10/2022 03/11/2022 N/A Bid 08/25/2023
Cross Island Parkway (US 278) Toll Conversion 05/18/2021 07/20/2021 07/26/2021 09/15/2021 12/16/2021 01/20/2022 N/A Bid 11/30/2022
Carolina Crossroads Phase 2 – Broad River Road at I-20 Interchange 07/15/2020 09/28/2020 10/02/2020 12/03/2020 08/09/2021 09/08/2021 11/15/2021 Bid 02/02/2025
Carolina Crossroads Phase 1 – Colonial Life Boulevard at I-126 Interchange 04/01/2020 06/29/2020 07/06/2020 09/01/2020 04/30/2021 05/12/2021 06/30/2021 Bid 10/14/2024
Interstate 77 Panther Interchange Project 07/28/2020 09/23/2020 09/24/2020 10/15/2020 12/15/2020 01/26/2021 01/29/2021 Bid 05/01/2023
Closed and Load Restricted Bridge Replacement Package 1-District 2 NA NA 09/30/2019 12/06/2019 06/03/2020 06/30/20 08/21/2020 Bid 08/25/2023
US-1 over I-20 Interchange Improvement 04/30/2019 07/15/2019 07/19/2019 09/03/2019 04/20/2020 05/29/2020 06/18/2020 Bid 06/07/2024
I-85 over Rocky Creek Bridge 03/04/2019 05/16/2019 05/22/2019 07/22/2019 01/23/2020 02/11/2020 03/30/2020 Bid 09/25/2023
I-26 Widening MM 85-101 03/29/2018 06/06/2018 06/07/2018 / 07/26/2018 08/23/2018 05/15/2019 05/24/19 08/01/19 Bid 04/21/2024
I-85 Widening MM 98-106 06/01/2017 07/27/2017 08/03/2017 09/14/2017 02/22/2018 03/15/2018 05/14/2018 Bid 09/29/2022
I-85 Reconstruction and Widening MM 77-98 02/05/2015 03/24/2016 04/13/2016 05/25/2016 09/28/2016 10/04/2016 01/12/2017 Bid 11/29/2023
I-20 Widening (MM 49 - 60) 01/29/2016 07/17/2015 09/15/2015 10/27/2015 01/29/2016 02/05/2016 04/15/2016 Bid 06/01/2022