SCDOT Design-Build Future Projects


Project Name RFQ Announcement
of Short-listed Teams
RFP Industry Review Final RFP Public Announcement STIP
Bridge Package 19 10/31/2024 12/17/2024 12/17/2024 01/10/2025 05/15/2025 STIP
Long Point Road Interchange Improvements March 2025 June 2025 June 2025 August 2025 February 2026 STIP
Bridge Package 27 March 2025 April 2025 April 2025 April 2025 May 2025 NA
Bridge Package 21 May 2025 June 2025 June 2025 July 2025 November 2025 NA
Bridge Package 22 November 2025 December
2025
December 2025 January 2026 May 2026 NA
Bridge Package 23 May 2026 June 2026 June 2026 July 2026 November 2026 NA
Bridge Package 24 Q4 2026 Q4 2026 Q4 2026 Q1 2027 Q2 2027 NA
Mark Clark Expressway Extension 2027 2027 2027 2027 2027 NA
Bridge Package 25 2027 2027 2027 2027 2027 NA
Bridge Package 26 2027 2027 2027 2028 2028 NA
Bridge Package 28 2028 2028 2028 2028 2028 NA
Lowcountry Corridor West 2028 2028 2028 2028 2028 STIP
Carolina Crossroads Phase 3 – I-20/26 & I-26/126 System Interchanges, St. Andrews Road at I-26 Interchange, and Bush River Road at I-20 Interchange 09/15/22 11/30/22 12/01/22 02/15/23 NA