SCDOT Design-Build Active Proposals


Project Name RFQ Announcement
of Short-listed Teams
RFP
Industry Review
Final RFP Bid Opening STIP
US 1 over I-20 Interchange Improvement 04/30/2019 07/15/2019 07/19/2019 September 2019 March 2020 STIP
I-26 Widening MM 85-101 03-29-2018 06-06-2018 06-07-2018 / 07-26-2018 08-23-2018 05-15-2019 STIP
I-85 over Rocky Creek Bridge 03/04/2019 05/16/2019 05/22/2019 July 2019 January 2020 STIP