SCDOT Design-Build Active Proposals


Project Name RFQ Announcement
of Short-listed Teams
RFP
Industry Review
Final RFP Public Announcement STIP
Long Point Road Interchange Improvements June 13, 2025 August 21, 2025 August 2025 October 2025 May 2026 STIP
Bridge Package 19 10/31/2024 12/17/2024 12/17/2024 01/10/2025 05/15/2025 STIP
Bridge Package 27 April 3, 2025 May 7, 2025 May 7, 2025 May 29, 2025 June 26, 2025 NA
I-95 over Lake Marion 10/7/2024 12/20/2024 1/8/2025 4/22/2025 9/11/2025 STIP
Carolina Crossroads Phase 3C 05/21/2024 08/06/2024 08/08/2024 10/08/2024 04/22/2025 STIP