Beginning on Friday night October 23, 2020, I-20 Westbound traffic will be shifted into a new configuration. The current westbound lanes will be shifted into the newly constructed lanes at approximate mile marker 60.5.
The shift will be performed over three days and traffic will be in several alignments as the temporary barrier wall is relocated and Exit ramps are realigned. On and Off-Ramps at Exit 58 and 55 will be closed at points over the weekend to allow for the realignment of ramps. Detours will be in place for these closures.
Traffic will be opened into the new configuration by Monday morning. A timeline of the traffic shift is detailed below.
Friday Night 10/23/2020
- I-20 Westbound Left Lane will be closed from Mile Marker 61 to Mile Marker 53.5 until Monday Morning at 6:00 AM
- Temporary Barrier will be relocated to allow for traffic to cross into the new lanes.
- The I-20 Westbound Left Lane will be shifted over onto the newly constructed through (left) lane. Traffic in this lane will be unable to exit until Exit 51.
- Traffic in the eastbound right lane will remain in the existing right lane and will have access to all exit ramps
Saturday Day and Night 10/24/2020
- Traffic will remain in a split alignment with the Westbound Left Lane traveling in the newly constructed through the lane and the Westbound Right Lane traveling in the existing right lane
- Temporary barrier wall and traffic control devices will be in the process of being relocated along the entire length of the project
Sunday Day 10/25/2020
- Traffic will remain in a split alignment with the Westbound Left Lane traveling in the newly constructed through the lane and the Westbound Right Lane traveling in the existing right lane
- Temporary barrier wall and traffic control devices will be in the process of being relocated along the entire length of the project
Sunday Night 10/25/2020
- The I-20 Westbound right lane will be closed and all traffic will be directed into the new through lane. At this point, Exit and Entrance Ramps at Exit 55 and 58 will be closed. All Westbound traffic will be unable to Exit until Exit 51.
- Barrier Wall, Traffic Control Devices, and Striping will be relocated on the ramps.
Monday Morning 10/26/2020
-
All Westbound I-20 Traffic will be completely shifted into the new alignment and all ramps will be opened by 6:00 AM
Message board signs along I-20, US1, and SC6, and Longs Pond Road will display any detour directions.
Motorists are advised to used caution and plan accordingly in case of delays.
The road work is part of a four-phase project to widen an 11-mile stretch of I-20 in Lexington County. The project extends from mile marker 60 near US 378 to mile marker 49 at Longs Pond Road. Upon completion, the project will add a third inside lane in both directions aimed at reducing traffic congestion. It is expected to be completed in the summer of 2021
Motorists can use SCDOT's 511 Traveler Info
http://www.511sc.org/
to check road conditions. For more information concerning this project, the public may contact SCDOT Resident Engineer John Burns at (803) 530-8798 or at