About the Project
SCDOT proposes to replace the S-250 (Hester Store Road) bridge over Machine Creek in Pickens County, SC. The proposed bridge will consist of two twelve-foot travel lanes in each direction. It is anticipated that the bridge will be constructed on existing alignment. To address immediate traffic concerns with the existing bridge closure, SCDOT intends to demolish the existing bridge and install a temporary bridge. This allows time for the permanent replacement design to be completed while providing immediate relief to the traveling public. Once construction for the permanent bridge is approved, the temporary bridge would be replaced with a new two-lane bridge. While the permanent bridge is being constructed, a temporary detour route will re-established.
Purpose and Need
The purpose of the project is to replace the existing bridge to meet current design and safety standards.
Due to deterioration and poor conditions, the current bridge is closed to all traffic and needs to be replaced.
Detour Map
Large Map View –Detour
The detour route recommended is to utilize Jim Hunt Road (S-39-305), Farrs Bridge Road (SC-183), and Old Dacusville Road (L-437). This detour route results in approximately 2.4 miles of additional mileage for the detoured motorists. Local citizens may take their preferred route of open roads. Please refer to the map to see the signed detour route.
Preliminary Engineering: | Underway |
---|---|
Public Outreach: | Spring 2024 |
Right of Way Aquisition: | Summer 2024 |
Demolition and Temporary Bridge Installed: | Summer 2024 |
Temporary Bridge Removed and Construction Begins: | Late 2024 |
Construction Duration: | Estimated at 24 months |