The dates below are a tentative timeline for the Environmental Impact Statement. Future dates are subject to slide within the project schedule.
| Month/Year | Milestone |
|---|---|
| Fall 2007 | Project Initiation - December 3, 2007 SCDOT formally notified FHWA of the intent to initiate the Environmental Impact Statement process for this project. |
| Winter 2008 | Notice of Intent published in the Federal Register |
| January 9, 2008 | Preparation for “Scoping” |
| Spring 2008 | Public Scoping Meeting |
| Agency Scoping Meeting | |
| Stakeholder Scoping Meetings | |
| Summer 2008 | SCDOT Develops Purpose and Need |
| Preparation of the DEIS | |
| Fall 2008 | Public Information Meetings |
| Winter 2009 | Preparation of the DEIS |
| Spring 2009 | Preparation of the DEIS |
| Summer 2009 | SCDOT Identifies and Recommends a Preferred Alternative. |
| Preparation of the DEIS | |
| Fall 2009 | Publication of DEIS - Public Hearing and Comment Period |
| Winter 2010 | Preparation of FEIS |
| Spring 2010 | Preparation of FEIS |
| Summer 2010 | Preparation of FEIS |
| Fall 2010 | Record of Decision |